Water Transmission Main Upgrade Project

Construction of the Town’s water transmission main upgrade project has begun. The Contractor doing the work is Pratt & Sons, Inc. from Minot, Maine. They began working this week along Weld Road near the Town office and will continue westerly along Weld Road now through June of this year. Work will then continue on Colby Miller, Orchard and North Pond Roads. The initial construction schedule is outlined below.

Estimated DatesWork Area
April – June 2025Weld Road from Doak Street to Colby Miller Road
Late April – Mid-May 2025Doak Street
June – August 2025Colby Miller Road
August – October 2025Orchard Drive and North Pond Road
Winter 2026Tree Clearing for North Pond Road Extension to Varnum Pond
Summer 2026Install Water Main from North Pond Road Extension to Varnum Pond
July 15 – September 20, 2026Replace intake in Varnum Pond
Sharing is caring, right?