Construction of the Town’s water transmission main upgrade project has begun. The Contractor doing the work is Pratt & Sons, Inc. from Minot, Maine. They began working this week along Weld Road near the Town office and will continue westerly along Weld Road now through June of this year. Work will then continue on Colby Miller, Orchard and North Pond Roads. The initial construction schedule is outlined below.
Estimated Dates | Work Area |
---|---|
April – June 2025 | Weld Road from Doak Street to Colby Miller Road |
Late April – Mid-May 2025 | Doak Street |
June – August 2025 | Colby Miller Road |
August – October 2025 | Orchard Drive and North Pond Road |
Winter 2026 | Tree Clearing for North Pond Road Extension to Varnum Pond |
Summer 2026 | Install Water Main from North Pond Road Extension to Varnum Pond |
July 15 – September 20, 2026 | Replace intake in Varnum Pond |